Chellow Manual

Licence

Chellow is released under the GPL v3.

Introduction

Chellow is a web application for checking UK electricity bills. It’s designed for organizations with high electricity consumption. The software is hosted at https://github.com/WessexWater/chellow.

Build Status

Installation

Chellow is a Python web application (with a built-in webserver) that uses the PostgreSQL database. To install Chellow, follow these steps:

  1. Install PostgreSQL 9.5

  2. Install Python 3.5 (tested on the CPython 3.5.3 interpreter)

  3. Create a PostgreSQL database called chellow with the character encoding UTF8.

  4. At the command line run:

    pip install chellow
  5. Set up the following environment variables to configure Chellow:

    Name Default Description

    PGUSER

    postgres

    Postgres user name

    PGPASSWORD

    postgres

    Postgres password

    PGHOST

    localhost

    Postgres host name

    PGPORT

    5432

    Postgres port

    PGDATABASE

    chellow

    Postgres database name

    CHELLOW_PORT

    80

    Port that the Chellow webserver will listen on

    in bash an environment variable can be set by doing:

    export CHELLOW_PORT=8080

    in Windows an environment variable can be set by doing:

    set CHELLOW_PORT=8080
  6. Start Chellow by running chellow start.

  7. You should now be able to visit http://localhost/ in a browser. You should be prompted to enter a username and password. Enter the admin user name ‘admin@example.com’ and the password ‘admin’, and then the home page should appear. Change the admin password from the ‘users’ page.

  8. Chellow can be stopped by running chellow stop.

Manual Upgrading

To upgrade to the latest version of Chellow enter the following at the command line:

chellow_updater.sh

Automatic Upgrading

On Unix, set up a cron job to regularly call the updater script by doing:

crontab -e

and entering the line:

\* * * * * source /home/me/venv/bin/activate;chellow_updater.sh

Using A Different Webserver

Chellow comes bundled with the Waitress webserver, but the is also a Python WSGI web application so Chellow can be used with any WSGI compliant application server, eg Gunicorn. The WSGI app that should be specified is chellow.app.

Detailed Instructions For Installing On CentOS 6.7 64 bit For Development

Install PostgreSQL 9.5.2

Add the PostgreSQL repository:

sudo rpm -ivh https://download.postgresql.org/pub/repos/yum/9.5/redhat/rhel-6-x86_64/pgdg-centos95-9.5-2.noarch.rpm

Install the PostgreSQL packages:

sudo yum install postgresql95 postgresql95-server postgresql95-contrib

Initialize the database:

sudo service postgresql-9.5 initdb

Make PostgreSQL start on boot:

sudo chkconfig postgresql-9.5 on

Edit PostgreSQL config file to accept all local connections:

sudo vi /var/lib/pgsql/9.5/data/pg_hba.conf

Find the lines:

local   all    all                    peer
host    all    all    127.0.0.1/32    peer

and change them to:

local   all    all                    trust
host    all    all    127.0.0.1/32    trust

start PostgreSQL:

sudo service postgresql-9.5 start

Install Python 3.5.1. Unfortunately there isn’t an rpm for this so we have to compile it:

sudo yum groupinstall "Development tools"
sudo yum install zlib-devel bzip2-devel openssl-devel ncurses-devel sqlite-devel readline-devel tk-devel gdbm-devel db4-devel libpcap-devel xz-devel wget
wget http://python.org/ftp/python/3.5.1/Python-3.5.1.tar.xz
tar xf Python-3.5.1.tar.xz
cd Python-3.5.1
./configure --prefix=/usr/local --enable-shared LDFLAGS="Wl,-rpath /usr/local/lib"
make
sudo make altinstall

We need to tell Chellow which port to listen on, so:

vi ~/.bashrc

and add the line:

export CHELLOW_PORT=8080
export PGUSER=postgres

Clone the Chellow source from GitHub:

git clone https://github.com/WessexWater/chellow.git

Change directory to the 'chellow' directory:

cd chellow

Create a local 'test' branch to track the remote 'origin/test' branch:

git branch --track test origin/test

Check out the 'test' branch into the working directory:

git checkout test

Create a Python virtual environment:

pyvenv-3.5 venv

Activate the environment:

source venv/bin/activate

Make sure you’re running a recent version of pip:

pip install --upgrade pip

Install tox:

pip install tox

Run tests:

tox

Getting Started

This is a brief guide to setting things up after you’ve installed Chellow.

View the Chellow home page

Assuming you’ve installed Chellow correctly, you should be able to open your browser, type in the URL of the Chellow application, and see the Chellow home page.

Users

Before any users are added, if you access Chellow from localhost you’ll have read / write access. Once users are added, you have to log in as one of those users. Users are added from the 'users' page.

Default users can be automatically assigned to requests from certain IP addresses. To associate an IP address to a user, go to the non-core contract configuration and add a line to the 'properties' field similar to the following:

{
  'ips': {'127.0.0.1': 'implicit-user@localhost'}
}

Note that multiple IP addresses can be mapped to the same user.

Add Sites

Sites can be added by hand from the the 'sites' link on the home page. If you’ve got a lot to enter, then you can import them using a CSV file.

Add Supplier Contracts

Click on 'supplier contracts' link and then fill out the 'Add a contract' form. For the Charge Script field enter:

def virtual_bill(data_source):
    data_source.supplier_bill['net-gbp'] = 0

This is the simplest possible virtual bill. To help with debugging you can print things out to the CSV file:

def virtual_bill(data_source):
    data_source.pw.println('The start date is ' +
  str(data.source.start_date))
    data_source.supplier_bill['net-gbp'] = 0

To use half-hourly data to generate a bill based on a day / night tariff, you can write:

from net.sf.chellow.billing import NonCoreContract
def virtual_bill(data_source):
    bill = data_source.supplier_bill
for hh in data_source.hh_data:
    if 0 < hh['utc-decimal-hour'] < 8:
        bill['night-kwh'] += hh['msp-kwh']
        bill['night-gbp'] += hh['msp-kwh'] * 0.05
    else:
        bill['day-kwh'] += hh['msp-kwh']
        bill['day-gbp'] += hh['msp-kwh'] * 0.1
bill['net-gbp'] = sum(v for k, v in bill.items() if k[-4:] == '-gbp')

For documentation on the languages that Chellow uses, see the Extending Chellow section.

Add HHDC Contracts

In the Properties text area you can set up a process that will check an FTP server every hour and download any new HH data files. Here’s an example:

has.importer=yes
file.type=.bg.csv
hostname=data.example.com
username=auser
password=apassword
directory0=.
mpan.map=searchtext>replacetext

Add Supplies

Supplies are imported in a similar way to sites above.

  • Source - Where the supply gets its electricity from.

net

    The DNO's network.
gen
Generator that's embedded within the site, so that the electricity generated displaces the electricity that would otherwise have to be imported from the DNO's network.

lm

    Load management generator
chp
    Combined heat and power.
turb
    Water turbine.
gen-net
    Generator that's directly connected to the DNO's network, so everything generated is exported to the network, and all parasitic electricity (imported by the generator) is imported from the network. Cf the source 'gen'. The generator types are the same as those available for the source 'gen'.
sub
    general sub-meter used for energy management.
3rd-party
    Where the electricity is from (or to) a party that is not the DNO.
3rd-party-reverse
As 3rd-party, but where the meter's import is measuring the export to the 3rd party.

Import HH data

HH data can be imported in a variety of formats. Chellow can also be set up to import files automatically from an FTP server.

Virtual Bills

To see the virtual bills for a supplier contract, go to the contract page and follow the Virtual Bills link.

Example Site

To set up an example site, insert a HHDC called 'IMSERV HH' with provider UKDC starting at 2010-06-01 and insert a supplier contract called 'SSE HH' with provider SOUT starting at 2010-05-01. Then save the General Import Format text below as a file with the extension '.csv' and then import it using the General Imports form. It’ll insert a site with a CHP supply and a supply from the network. It’ll also put in some HH data for the beginning of October 2010.

"insert","site",78342,"Stowford Manor"
"insert","supply",78342,"net",,"Main","_L","2010-10-01",,,,"IMSERV HH",2,"TRUE","TRUE","TRUE","TRUE","PO98881",0,845,5,,"22 0000 0000 111",520,200,"SSE HH",933,"22 00000000120",521,80,"SSE HH",45
"insert","hh-datum","22 0000 0000 111","2010-10-01","TRUE","TRUE","22,A,0,A,59,A,105,A,0,A,0,A,8,A,114,A,0,A,52,A,0,A,7,A,23,A,23,A,36,A,112,A,0,A,0,A,0,A,24,A,0,A,7,A,57,A,48,A,0,A,96,A,57,A,66,A,0,A,85,A,0,A,8,A,0,A,123,A,0,A,0,A,84,A,0,A,21,A,0,A,19,A,47,A,0,A,0,A,24,A,0,A,0,A,5,A,1,A,0,A,0,A,11,A,0,A,0,A,0,A,14,A,0,A,111,A,0,A,24,A,105,A,0,A,5,A,2,A,0,A,0,A,0,A,0,A,43,A,94,A,0,A,0,A,0,A,2,A,17,A,36,A,27,A,0,A,0,A,13,A",,,,,,,,,,,,,,,,,,,,,,,,,
"insert","hh-datum","22 0000 0000 111","2010-10-01","FALSE","TRUE","0,A,57,A,0,A,0,A,45,A,81,A,0,A,0,A,54,A,0,A,114,A,0,A,0,A,0,A,0,A,0,A,54,A,29,A,126,A,0,A,2,A,0,A,0,A,0,A,33,A,0,A,0,A,0,A,88,A,0,A,72,A,0,A,55,A,0,A,19,A,8,A,0,A,0,A,0,A,34,A,0,A,0,A,37,A,92,A,0,A,73,A,118,A,0,A,0,A,64,A,83,A,0,A,14,A,103,A,20,A,0,A,57,A,0,A,58,A,0,A,0,A,32,A,0,A,0,A,8,A,12,A,88,A,82,A,0,A,0,A,55,A,31,A,74,A,0,A,0,A,0,A,0,A,99,A,44,A,0,A"
"insert","supply",78342,"gen","chp","CHP","_L","2010-10-01",,,,"IMSERV HH",3,"TRUE","FALSE","TRUE","FALSE","PO6755",0,845,5,,"99 0000 0000 015",510,100,"SSE HH",6,,,80,"SSE HH",45
"insert","Hh-datum","99 0000 0000 015","2010-10-01",TRUE,TRUE,"62,A,82,A,24,A,29,A,63,A,115,A,81,A,6,A,150,A,33,A,131,A,51,A,14,A,102,A,30,A,37,A,113,A,40,A,146,A,87,A,29,A,19,A,60,A,90,A,79,A,20,A,48,A,20,A,143,A,29,A,138,A,135,A,129,A,19,A,41,A,125,A,2,A,123,A,92,A,131,A,96,A,65,A,149,A,139,A,114,A,97,A,147,A,56,A,136,A,99,A,140,A,26,A,31,A,136,A,113,A,3,A,148,A,15,A,131,A,102,A,42,A,34,A,82,A,39,A,43,A,35,A,92,A,104,A,37,A,56,A,143,A,119,A,122,A,94,A,105,A,111,A,118,A,149,A,82,A,15,A"

Data Model

  • Sites

  • Supplies

  • Supply Generations

  • Site

  • Supplier Contract

  • DC Contract

  • Channels

  • HH Data

  • Profile Class

  • Import / Export

  • Mpan Core

  • LLFC

  • Supply Capacity

  • Supplier Contracts (Same for DC and MOP)

  • Rate Scripts

  • Batches

  • Bills

  • Supply

  • Register Reads

  • DNOs (Distribution Network Operators)

  • LLFCs (Line Loss Factor Classes)

General Import Formats

Key points when importing

  • Lines beginning with the '#' character are comment lines.

  • You can import any number of lines, and mix actions and types in a single file.

  • When updating a record, if the field contains {no change}, then that field won’t be updated.

  • A blank date field means 'ongoing'.

Action Type

insert

site

Site Code

Site Name

delete

site

Site Code

update

site

Current Site Code

New Site Code

Site Name

insert

supply

Site Code

Source Code

Generator Type

Supply Name

GSP Group (geographic location)

Start date (yyyy-MM-dd)

Finish Date

MOP Contract

MOP Account

HHDC Contract

HHDC Account

Meter Serial Number

Profile Class

Meter Timeswitch Class

CoP

Standard Settlement Configuration (blank for HH supplies)

Import MPAN Core

Import LLFC

Import Supply Capacity

Import Supplier Contract

Import Supplier Account

Export MPAN Core

Export LLFC

Export Supply Capacity

Export Supplier Contract

Export Supplier Account

update

supply

MPAN Core

Source Code

Generator Type

Supply Name

GSP Group

insert

era

MPAN Core

Start date (yyyy-MM-dd)

Site Code

MOP Contract

MOP Account

HHDC Contract

HHDC Account

Meter Serial Number

Profile Class

MTC

CoP

SSC

Import MPAN Core

Import LLFC

Import Supply Capacity

Import Supplier Contract

Import Supplier Account

Import ACTIVE?

Import REACTIVE_IMP?

Import REACTIVE_EXP?

Export MPAN Core

Export LLFC

Export Supply Capacity

Export Supplier Contract

Export Supplier Account

Export ACTIVE?

Export REACTIVE_IMP?

Export REACTIVE_EXP?

update

era

MPAN Core

Date

Start date

Finish date

MOP Contract

MOP Account

HHDC Contract

HHDC Account

Meter Serial Number

Profile Class

MTC

CoP

SSC

Import MPAN Core

Import LLFC

Import Supply Capacity

Import Supplier Contract

Import Supplier Account

Export MPAN Core

Export LLFC

Export Supply Capacity

Export Supplier Contract

Export Supplier Account

delete

era

MPAN Core

Date

insert

channel

MPAN Core

Date (yyyy-MM-dd hh:mm)

Import Related?

Channel Type (active, reactive import, reactive export)

delete

channel

MPAN Core

Date

Import Related?

Channel Type (active, reactive import, reactive export)

insert

site_era

Site Code

Core MPAN

Era Start Date

Is Physical?

insert

hh_datum

MPAN Core

Date

Channel Type

Value

Status

insert

user

Email Address

Password

Password Digest

User Role

Participant Code

Role Code

update

user

Current Email Address

Email Address

Password

Password Digest

User Role

Participant Code

Role Code

insert

channel_snag_ignore

MPAN Core

Is Import?

Is kWh?

Description

From

To

insert

site_snag_ignore

Site Code

Description

From

To

insert

batch

Role Name (hhdc, supplier or mop)

Contract Name

Reference

Description

update

batch

Role Name (hhdc, supplier or mop)

Contract Name

Old Reference

New Reference

Description

insert

bill

Role Name(hhdc, supplier or mop)

Contract Name

Batch Reference

Mpan Core

Issue Date

Start Date

Finish Date

Net

Vat

Gross

Account Reference

Reference

Type

Breakdown

Kwh

(Meter Serial Number

Mpan

Coefficient

Units

TPR

Previous Date

Previous Value

Previous Type

Present Date

Present Value

Present Type)*

update

bill

Chellow Id

Account

Reference

Issue Date

Start Date

Finish Date

kwh

Net

Vat

Type

Paid?

Breakdown

update

register_read

Chellow Id

TPR

Coefficient

Units

Meter Serial Number

MPAN

Previous Date

Previous Value

Previous Type

Present Date

Present Value

Present Type

insert

llfc

DNO Code

LLFC Code

LLFC Description

Voltage Level Code

Is Substation?

Is Import?

Valid From

Valid To

delete

llfc

DNO Code

LLFC Code

Date

HH Data Formats

Below are all the HH data formats accepted by Chellow. Chellow recognizes them by their filename extension. The files may be compressed as zip files.

Stark DF2

File extension .df2.

The data file is of the form:

#F2
#O 99 9999 9999 999
#S 2
27/07/05,00:30,95.4,A
27/07/05,01:00,93.8,A
27/07/05,01:30,91.9,A

Values Of The Sensor Number S

Number Meaning

1

Import kWh

2

Export kWh

3

Import kVArh

4

Export kVArh

and the status character on the end is optional. For the newer six-channel meters the channels are mapped to the DF2 format as follows:

Import Related

Export Related

Active kWh

#O mpan_core
#S 1

#O mpan_core
#S 2

Reactive Import kVArh

#O import_mpan_core
#S 3

#O export_mpan_core
#S 3

Reactive Export kVArh

#O import_mpan_core
#S 4

#O export_mpan_core
#S 4

CSV Simple

File extension .simple.csv.

A CSV file with the following columns:

Name Description

MPAN Core

Channel Type

'ACTIVE', 'REACTIVE_IMP' or 'REACTIVE_EXP'

Time

Half-hour starting yyyy-MM-dd hh:mm

Value

Status

'A' - actual, 'E' - estimate, 'C' - padding.

Here’s an example:

MPAN core, Channel Type, Time, Value, Status
99 9999 9999 999, ACTIVE, 2006-01-01 00:30, 218.4 , E
99 9999 9999 999, ACTIVE, 2006-01-01 01:00, 220.4 , E
99 9999 9999 999, ACTIVE, 2006-01-01 01:30, 221.8 , E
99 9999 9999 999, ACTIVE, 2006-01-01 02:00, 223.4 , E
99 9999 9999 999, ACTIVE, 2006-01-01 02:30, 224.6 , E
99 9999 9999 999, ACTIVE, 2006-01-01 03:00, 226.8 , E
99 9999 9999 999, ACTIVE, 2006-01-01 03:30, 203.8 , E
99 9999 9999 999, ACTIVE, 2006-01-01 04:00, 155.2 , E
99 9999 9999 999, ACTIVE, 2006-01-01 04:30, 169.0 , E
99 9999 9999 999, ACTIVE, 2006-01-01 05:00, 171.0 , E

bGlobal CSV

File extension .bg.csv.

A CSV file with the following columns:

Name Description

MPAN core

Meter Serial Number

Date

dd/MM/yy

HH 1

kWh in 1st HH

HH 2

kWh in 2nd HH

HH 3

kWh in 3rd HH

…​

…​

HH 48

kWh in 48th HH

Here’s an example:

9999999999999,E04M00872,06/07/2008,0.262,0.26,0.252,0.246,0.249,0.251,0.25,0.249,0.244,0.239,0.255,0.255,0.286,0.289,0.356,0.489,0.576,0.585,0.496,0.411,0.457,0.463,0.436,0.447,0.436,0.431,0.439,0.396,0.455,0.453,0.377,0.314,0.341,0.338,0.418,0.45,0.446,0.442,0.464,0.366,0.314,0.386,0.395,0.444,0.346,0.288,0.263,0.255,0,0
9999999999999,E04M00872,07/07/2008,0.247,0.216,0.211,0.227,0.237,0.233,0.229,0.204,0.225,0.267,0.301,0.324,0.466,0.471,0.475,0.546,0.505,0.382,0.362,0.434,0.387,0.395,0.35,0.378,0.348,0.356,0.301,0.34,0.337,0.396,0.386,0.388,0.369,0.325,0.356,0.36,0.367,0.429,0.427,0.466,0.404,0.403,0.319,0.359,0.299,0.294,0.264,0.29,0,0
9999999999999,E04M00872,08/07/2008,0.312,0.31,0.254,0.237,0.222,0.226,0.218,0.211,0.225,0.263,0. 262,0.283,0.423,0.495,0.561,0.569,0.496,0.41,0.381,0.355,0.323,0.366,0.4,0.363,0.381,0.396, 0.392,0.369,0.317,0.301,0.378,0.311,0.391,0.345,0.344,0.382,0.436,0.384,0.353,0.34,0.335,0.352,0.388,0.394,0.389,0.346,0.284,0.258,0,0
9999999999999,E04M00872,09/07/2008,0.246,0.246,0.257,0.266,0.251,0.24,0.229,0.236,0.232,0.245,0.268,0.289,0.424,0.46, 0.513,0.481,0.459,0.441,0.368,0.348,0.401,0.403,0.413,0.412,0.371,0.396,0.381,0.321,0.321,0.276,0.303,0.311,0.348,0.33,0.381,0.398,0.372,0.38,0.322,0.342,0.349,0.331,0.439,0.41,0.368,0.326,0.274,0.257,0,0
9999999999999,E04M00872,10/07/2008,0.247,0.247,0.242,0.251,0.243,0.254,0.25,0.243,0.245,0.246,0.252,0.336,0.378,0.49,0.443, 0.467,0.544,0.467,0.375,0.387,0.403,0.347,0.415,0.404,0.422,0.42,0.375,0.385,0.371, 0.371,0.359,0.397,0.402,0.384,0.393,0.389,0.365,0.381,0.498,0.402,0.355,0.326,0.311,0.31,0.342,0.274,0.293,0.313,0,0
9999999999999,E04M00872,11/07/2008,0.303,0.303,0.277,0.244,0.254,0.24,0.249,0.256,0.318,0.318,0.305, 0.299,0.421,0.529,0.547,0.452,0.458,0.423,0.433,0.377,0.344,0.401,0.417,0.392,0.364,0.373,0.367,0.376,0.387,0.378,0.521,0.525,0.413,0.42,0.377,0.42,0.367,0.371,0.336,0.341,0.336,0.4,0.413,0.401,0.407,0.376,0.353,0.338,0,0
9999999999999,E04M00872,12/07/2008,0.324,0.319,0.31,0.31,0.312,0.282,0.232,0.244,0.246,0.252,0.268,0.286,0.329, 0.378,0.547,0.444,0.447,0.535,0.631,0.556,0.473,0.503,0.47,0.402,0.419,0.443,0.442, 0.409,0.378,0.366,0.384,0.392,0.403,0.406,0.481,0.541,0.486,0.405,0.366,0.364, 0.364,0.43,0.436,0.386,0.402,0.322,0.279,0.291,0,0
9999999999999,E04M00872,13/07/2008,0.268,0.272,0.261,0.25,0.311,0.306,0.267,0.259,0.26,0.3,0.333,0.326,0.362, 0.37,0.448,0.458,0.567,0.664,0.781,0.609,0.529,0.566,0.464,0.366,0.388,0.423,0.357,0.41, 0.352,0.357,0.486,0.547,0.52,0.516,0.558,0.639,0.607,0.65,0.637,0.483,0.457,0.51,0.444,0.422,0.442,0.4,0.314,0.347,0,0
9999999999999,E04M00872,14/07/2008,0.32,0.344,0.261,0.304,0.309,0.239,0.302,0.312,0.26,0.334,0.265,0.444,0.488, 0.552,0.543,0.58,0.599,0.501,0.497,0.48,0.334,0.376,0.409,0.405,0.314,0.303, 0.329,0.369,0.299,0.436,0.48,0.527,0.499,0.549,0.37,0.373,0.347,0.339,0.348, 0.412,0.425,0.385,0.423,0.376,0.373,0.353,0.281,0.27,0,0
9999999999999,E04M00872,15/07/2008,0.314,0.309,0.298,0.29,0.291,0.236,0.244,0.24,0.239,0.246,0.265,0.308, 0.414,0.428,0.504,0.527,0.472,0.35,0.483,0.485,0.543,0.519,0.45,0.345,0.347, 0.375,0.455,0.509,0.498,0.469,0.304,0.329,0.413,0.397,0.445,0.534,0.506,0.405, 0.447,0.422,0.48,0.42,0.431,0.418,0.387,0.365,0.281,0.263,0,0
9999999999999,E04M00872,16/07/2008,0.279,0.313,0.316,0.314,0.311,0.311,0.303,0.287,0.239,0.261,0.269, 0.342,0.446,0.491,0.445,0.556,0.503,0.463,0.412,0.407,0.472,0.445,0.417,0.394, 0.391,0.368,0.403,0.384,0.37,0.316,0.39,0.353,0.442,0.424,0.555,0.477,0.525, 0.476,0.39,0.464,0.465,0.399,0.427,0.432,0.428,0.371,0.333,0.269,0,0

Importing Bills

To import bills for a particular contract, create a batch, and then upload the bill file. The following electricity bill formats can be imported. Chellow recognizes the format by the file extension.

Format Extension

EDF Energy Proprietary

mm

CSV

csv

BGB EDI File

bgb.edi

SSE EDI File

sse.edi

GDF CSV

gdf.csv

CSV Format

CSV file with the following columns:

# Bill Type (N - Normal, W - Withdrawn or F -Final)

Account Reference

Mpans

Invoice Reference

Issue Date (YYYY-mm-dd HH:MM)

Start Date (YYYY-mm-dd HH:MM)

Finish Date (YYYY-mm-dd HH:MM)

kWh

Net

VAT

Gross

Breakdown

R1 Meter Serial Number

R1 MPAN

R1 Coefficient

R1 Units (kWh, kW, kVA or kVArh

Blank if kW or kVA)

R1 TPR

R1 Previous Read Date

R1 Previous Read Value

R1 Previous Read Type

R1 Present Read Date

R1 Present Read Value

Read Types

Chellow Code Chellow Description sse.edi Code sse.edi Description bgb.edi Code bgb.edi Description

N

Normal

00

Normal Reading

00

Normal Reading - Default

N3

Normal 3rd Party

09

Third Party Normal Reading

C

Customer

04

Customer’s Own Reading

04

Customer’s own reading

E

Estimated

02

Estimated (Computer) Reading

02

Estimated (computer)

E3

Estimated 3rd Party

11

Third Party Estimated (Computer) Reading

EM

Estimated Manual

01

Estimated (manual)

W

Withdrawn

03

Removed meter reading

X

Exchange

06

Exchange Meter Reading

06

Exchange Meter Reading

CP

Computer

05

Computer Reading

IF

Information

12

Reading for Information only

Common Tasks

Merging Two Supplies

Say there are two supplies A and B, and you want to end up with just A. The steps are:

  1. Back up the data by taking a snapshot of the database.

  2. Check that A and B have the same header data (LLFC, MTC etc).

  3. See if there are any overlapping channels, eg. do both A and B have import kVArh? If there are, then decide which one is going to be kept.

  4. Load the hh data for the required channels from the backup file. First take a copy of the file, then edit out the data you don’t want, then further edit the file so that it loads into the new supply.

  5. Delete supply B.

Reports

Name Description

metered-import-*

Uses HH data for HH and AMR supplies, and register reads for dumb NHH supplies.

metered-import-estimated-kwh

For HH data, the kWh with the 'E' flag.

billed-import-*

A daily rate is calculated for a bill, and applied to the number of days it covers of the month in question.

Supplies Monthly Duration

Here’s how Chellow calculates the monthly consumption for dumb NHH supplies. First it finds the closest normal reads. Let’s assume there are just two for simplicity. For each TPR, Chellow works out the (historical kWh / hh) = (kWh between the two reads) / (number of HHs between the two reads). Then Chellow finds the number of HHs between the beginning of the month and the end of the month, and also the number of HHs that fall within the TPR, between the beginning and and of the month. The kWh for each half hour in the month for each TPR is (historical kWh / hh) * (month half-hours) / (month half-hours within TPR).

Bills

A row for each bill that falls within the given period.

Local Reports

Core reports come with Chellow and have odd ids. User reports are created by users and have even numbers. Reports are written in Python, and often use a Jinja2 template. You can display a link to a report of user reports by adding the following line to the configuration:

local.reports=82

replacing 82 with the id of the report of reports that you’ve created.

Design Decisions

Why don’t you use the +/- infinity values for timestamps? The problem is that it’s not clear how this would translate into Python. So we currently use null for infinity, which naturally translates into None in Python.

About

Web application for checking UK electricity bills

Resources

Stars

Watchers

Forks

Releases

No releases published

Packages

No packages published

Languages

  • Python 80.1%
  • HTML 14.7%
  • CSS 5.1%
  • Other 0.1%